US 41 Utility Improvements

Project Description

This project includes extending sewer lines to provide service to certain developed properties within five project areas along the improved US 41 Corridor.

Project Location

Five commercial areas between Collingswood Boulevard to Cornelius Boulevard. 

Latest Updates

All affected businesses along the project route have been contacted. The project will start with area four. Area four is in final design and easements are being acquired. Preliminary studies for areas 1 and 2 are complete, and the department is coordinating with the developers. Area 5 is complete.

If you are a business along the project and your septic system is in failure, please call us at 941-764-4300.

Budget

Phase Cost
Total Budget $713,000

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 11/01/2020 11/30/2023

Project Phase
Planning and Project Approval

Last Updated
10/30/2024