Project Description
This project includes extending sewer lines to provide service to certain developed properties within five project areas along the improved US 41 Corridor.Project Location
Five commercial areas between Collingswood Boulevard to Cornelius Boulevard.Latest Updates
All affected businesses along the project route have been contacted. The project will start with area four. Area four is in final design and easements are being acquired. Preliminary studies for areas 1 and 2 are complete, and the department is coordinating with the developers. Area 5 is complete.
If you are a business along the project and your septic system is in failure, please call us at 941-764-4300.
Budget
Phase | Cost |
---|---|
Total Budget | $713,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 11/01/2020 | 11/30/2023 |
Project Phase
Planning and Project Approval
Last Updated
10/30/2024
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities