Project Description
This project involves removing and replacing the sewer force mains within the road right of ways and utility easements. The project starts at the East Port Reclamation Facility, across I-75, and through the Deep Creek neighborhood ending at the Angol Street lift station. These new sewer force mains will increase transmission capacity for the Deep Creek neighborhood. Road construction, which includes road cuts, will occur at Rampart Boulevard, Deep Creek Boulevard, Rio de Janeiro Avenue, and other cross streets for the project. We also will be making pumping improvements at several sewer lift stations along the same corridor.Project Location
Throughout the Deep Creek neighborhood starting at Rampart Boulevard to Rio de Janeiro Avenue along the east side of the roadway and ending at the Angol Street lift station.
Project Impacts
The project had to be field engineered due to a kink in the 48" inch casing running under I-75. The original design included the new 24” pvc pipe to run through the casing.
Acquisition of valves has delayed a portion of the project.
Latest Updates
Construction will start at the East Port Water Reclamation Facility and will move east. Construction materials are being stored at the corner of Sandhill Boulevard and Rio de Janeiro Avenue.
Budget
Phase | Cost |
---|---|
Construction | $3,659,157.17 |
Total Budget | $3,659,157.17 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 08/12/2020 | 10/31/2022 | 11/01/2022 |
Turnover & Closeout | 11/01/2022 | 03/31/2023 | 03/31/2023 |
Supporting Materials
Project Phase
Project Complete
Last Updated
04/11/2023
Project Manager
Dean Campbell
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities
Construction Contractor
Cobb Site Development Inc.